Fred. Olsen Seawind and Vattenfall JV complete grid connection route scenarios study and confidently select preferred connection for Muir Mhòr project, with Optioneer

17

Landfall locations options analysed.

5

Substations locations options analysed.

8 weeks

To arrive at preferred grid connection option.

The challenge

With HND in the equation, the traditional methods of route optioneering would not have allowed for all possible grid connection options to be evaluated in a sufficient level of detail and within the time available. The Muir Mhòr team needed to try another approach to get results confidently whilst managing the tight deadlines set by HND.

Muir Mhòr is a floating offshore wind farm project located off the east coast of Scotland.

A joint venture between Fred. Olsen Seawind and Vattenfall, the project is scheduled to generate in 2030, putting the UK on track to meet its target of 5GW of floating wind by 2030.

ScotWind was the first round of offshore wind leasing in Scottish waters for over a decade. The round resulted in 20 projects securing seabed option agreements, including Muir Mhòr.

A first of its kind, Scotwind was also split into two tranches when it came to grid connections: Holistic Network Design (HND) and Holistic Network Design Follow-Up Exercise (HNDFUE). The HND was defined by National Grid ESO, outlining the ways in which the system operator plans on providing the required transmission infrastructure for connecting all planned offshore wind. In principle, coordinating offshore connections in HND was a logical approach, but in practice, this introduced a lot of uncertainty regarding the connection process for developers.

The process

The Muir Mhòr team wanted to be proactive in gaining a sufficient understanding of the project space – which extended from Moray to the East Midlands – without expending multi-million-pound on survey vessels until greater project certainty was achieved, and to be well prepared for what the HND process might out-turn. The prospective HND process offered an immediate opportunity to test Optioneer in earnest.

Optioneer was used to assess a long list of export cable routes connecting 17 potential landfalls, 5+ onshore substation locations and multiple wind farm exit points.

The tool captured knowledge from industry experts and integrated it into a robust model for assessing all feasible connection options. The model included environmental, social, engineering and cost considerations in line with policy and objectives of the Holistic Network Design exercise.

Coupled with reviews by subject matter experts from each discipline, this approach offered quantitative certainty over the route options’ viability by comparing all connection scenarios and, within those, comparing the preferable route options against environmental, technical and social criteria.

Optioneer also provided a visual and interactive environment with detailed routing analysis for engaging with key stakeholders.

With Optioneer, the Muir Mhòr team was given the greatest confidence in their grid connection options, with the flexibility to understand the various scenarios as the wider HND picture was developing.

The Muir Mhòr team wanted to be proactive in gaining a sufficient understanding of the project space – which extended from Moray to the East Midlands – without expending multi-million-pound on survey vessels until greater project certainty was achieved, and to be well prepared for what the HND process might out-turn. The prospective HND process offered an immediate opportunity to test Optioneer in earnest.

Optioneer was used to assess a long list of export cable routes connecting 17 potential landfalls, 5+ onshore substation locations and multiple wind farm exit points.

The tool captured knowledge from industry experts and integrated it into a robust model for assessing all feasible connection options. The model included environmental, social, engineering and cost considerations in line with policy and objectives of the Holistic Network Design exercise.

Coupled with reviews by subject matter experts from each discipline, this approach offered quantitative certainty over the route options’ viability by comparing all connection scenarios and, within those, comparing the preferable route options against environmental, technical and social criteria.

Optioneer also provided a visual and interactive environment with detailed routing analysis for engaging with key stakeholders.

With Optioneer, the Muir Mhòr team was given the greatest confidence in their grid connection options, with the flexibility to understand the various scenarios as the wider HND picture was developing.

The Muir Mhòr project team

The results

Optioneer enabled the Muir Mhòr team to gain greater certainty on the viability of connection options and reach the conclusion of their preferred option without spending multi-£Million on survey vessels without prior extensive desktop study.

Optioneer enabled the Muir Mhòr team to gain greater certainty on the viability of connection options and reach the conclusion of their preferred option without spending multi-£Million on survey vessels without prior extensive desktop study.

Industry uncertainty managed through quick adaptation via AI.

Early regulator engagement achieved optimal connection outcome & consent application.

Consent achieved, leveraging detailed options assessment from Optioneer.

“We can run a route in half a day with Optioneer compared to weeks with GIS only. As well as saving us a considerable amount of time, the platform took away a lot of the desk work and allowed our specialists to focus on what they do best. It gave us the knowledge and confidence we needed going into the HND exercise. The platform itself is visually impressive and has proven a helpful collaborative working tool for external stakeholder interactions, as well as internal multi-disciplinary meetings. ”
Helen Snodin
Senior Grid and Regulations Manager
The Muir Mhòr project team

Have you got a similar project to deliver?

Reach out today and see how Optioneer can help streamline your project planning and development.

Discuss your project
Learn how Optioneer can accelerate your project development programmes
Ready to revolutionise your project development process? Schedule a no-obligation discussion with our team.
OPTIONEER CAN HELP YOU TO
Cut programme length
Demonstrate a robust selection process
Build consensus with key stakeholders
We’ll help you succeed
Our team of product experts will help set up your project in Optioneer and ensure you and your team achieve your goals.
 *
Please fill in the first name
 *
Please fill in the last name
 *
Please fill in a valid email
Please fill in the company name

By clicking the Get in touch button you accept Continuum Industries’ Privacy Policy and agree to receive promotional messages from Continuum Industries about its products and services. You can unsubscribe at any time by clicking on the link at the bottom of our emails.

Clock
Thank you for contacting us!

We will be in touch with you shortly.

Oops! Something went wrong while submitting the form.