.{ background: linear-gradient(-45deg, #1ccdd8, #29194f, #1fa6ba, #29194f, #29194f); background-size: 400% 400%; animation: ci-gradient 10s ease infinite; } @keyframes ci-gradient { 0% { background-position: 0% 50%; } 50% { background-position: 100% 50%; } 100% { background-position: 0% 50%; } }
Strategy & network

Make capital decisions on defensible, spatial evidence.

The challenge for strategy and investment teams isn’t just cost—it’s deliverability. Schemes that are technically sound on paper often fall apart when they meet the friction of reality. Optioneer connects system-level thinking to spatial feasibility from the start.

Network development
System planning
Asset strategy
Capital planning
Regulatory affairs

Feasibility-informed network planning

Evaluate connections and asset interventions against real spatial constraints, not just assumptions. Understand where physical buildability and cost diverge before locking into a development path.

System scenario modelling

Run parallel "what-if" configurations across your network—alternative connection strategies, phasing sequences, or multi-vector co-location—without waiting for engineering teams to manually generate options.

Portfolio 
optimisation

Rank and sequence projects within a capital programme using real-world routing feasibility, land access risk, and early-stage CAPEX. So you can understand which projects are deliverable, and in what order.

Regulatory-grade evidence

Maintain an auditable record of every option assessed, constraint applied and decision made. Move from "good practice" to a regulatory ready, fully defensible and objective planning process.

In practice: Real-world defensibility

Global scale assessment

A major European TSO evaluated over 10,000 km of strategic hydrogen corridors across multiple future scenarios—a country-scale assessment completed within a realistic programme window.

Accelerated planning

A British utility leveraged early-stage Optioneer analysis to bring network plans forward by up to three years.

Related use cases:
GIS & engineering

From strategic corridor to preferred alignment — faster, more rigorous.

Engineers and GIS teams spend a disproportionate amount of time on manual data assembly, iteration and re-running analysis every time a constraint changes. Optioneer automates the baseline so your team can focus on the calls that actually require engineering judgement.

Routing & siting
GIS analysts
Technical feasibility
Civil & geotechnical

Ready-to-use spatial data

97% of the data you need is already in the platform. Add your own layers, define constraint weights, and generate corridors in minutes — not weeks of GIS preparation.

Automated option generation

Run automated option generation from origin to destination, respecting defined constraint hierarchies. Output a set of scored, ranked options ready for team review.

Integrated technical screening

Slope analysis, terrain crossings, ground condition proxies, access feasibility — surface and flag issues before programme commitments are made, on every route option, not just the preferred one.

Asset type 
optimisation

Switch asset type based on topography, designations, and policy constraints — with cost implications updating automatically as you iterate, based on the parameters you defined upfront.

Engineering impact: Verified results

93% faster

In an official Energy Networks Association study, National Gas observed a 93% reduction in routing time using Optioneer. With the Optioneer software-generated results closely matching expert-designed routes.

Voltage upgrade viability

A California-based utility uses Optioneer to evaluate the viability of following existing RoWs while upgrading assets from 138kV to 220kV, ensuring any assets avoid constraints that have arisen post-completion of the existing line.

Related use cases:
Environment & permitting

Identify, quantify, and avoid environmental risk — in early stage planning.

Environmental planners and permitting leads face a familiar problem: the option is effectively fixed before they're fully engaged. But Optioneer brings environmental analysis to the option origination process. So risks are not just mitigated, but avoided entirely.

Environmental planners
EIA co-ordinators
Permitting & consent managers
Ecology & biodiversity
Landscape & LVIA
Water & hydrology

Surface risks early

Overlay protected habitats, heritage assets, hydrological features, and landscape designations to produce a comparative environmental risk score for every option.

EIA & screening support

Export constraint maps, designated area summaries, and impact tables directly into EIA screening submissions. The foundation is ready for expert interpretation.

Biodiversity assessment

Continuum Industries' BNG baseline dataset enables desktop-level biodiversity impact assessments per route option — identifying high-value habitats early.

Cumulative impact assessment

Model other planned or consented developments alongside your own. Meet the increasing regulatory demand for cumulative analysis.

Environmental ROI: Proven at scale

Over £10 million in cost savings

By identifying forestry and ecological constraints at the option stage—before ground investigations or surveys—customers have selected alternative alignments that avoided tens of millions of pounds in mitigation costs.

Successfully consented projects

There are thousands of kilometres of infrastructure in construction, or already in operation, which used Optioneer at the early stages of development. A solid data-driven foundation supports later detailed studies and challenges, accelerating the overall development timeline.

Related use cases:
Commercial & Grid Connection

Maximise bid wins and minimise development risk.

Commercial teams work at the front end of the project lifecycle — where information is limited, timelines are compressed, and the cost of a bad decision is a wasted development budget or a lost bid. Optioneer compresses the time from opportunity to credible, costed position.

Business development
Project origination
Grid connection / Interconnection
Competitive tenders
Developers & IPPs
M&A due diligence

Pre-commitment screening

Evaluate candidate grid connection points, interconnection feasibility and locations for renewable energy projects at site-identification stage. Know the routing constraints before you commit resources.

Rapid bid development

For CATO, FERC1000, or equivalent frameworks, the window to submit is narrow. Optioneer evaluating millions of possible options, enables rapid feasibility assessments, and early CAPEX estimates that hold up to technical and cost scrutiny.

Spatially grounded go/no-go

Produce defensible cost-risk profiles early to inform investment decisions and regulatory submissions — not a number on a spreadsheet, but a spatially grounded estimate with a documented constraint basis.

Repurposing vs. new-build

Evaluate whether existing assets can be repurposed or upgraded, with constraint and cost comparisons against greenfield alternatives. Understand the delta before the business case is written.

Commercial impact: Speed to market

The "12,000 mile" sprint

During a competitive tender window, one customer evaluated over 12,000 miles of transmission. This was completed by a team of just three people in a matter of weeks—a scale of analysis previously impossible without Optioneer.

Long-term strategy

Three British gas utilities used Optioneer to model repurposing vs. new-build scenarios across their existing networks. This analysis didn't just inform a project; it defined their long-term network strategy and capital programme.

Related use cases:
Stakeholder & public engagement

Build a defensible, transparent record that holds up to scrutiny.

Stakeholder teams are increasingly asked to defend not just the development, but the process that produced it. Objections to infrastructure projects now routinely target the adequacy of the alternatives assessment — not just the outcome. Optioneer provides the visual materials and evidence needed to turn challenges into consensus.

Stakeholder engagement leads
Public affairs & PR
Community liaison
Communications
In practice: Trust earned through data

Defense against challenges

A Scottish developer used Optioneer to demonstrate a rigorous and defensible options process after receiving a community-led legal challenge on alternative routes — converting the challenge into an auditable record.

18 months of visual clarity

For one major infrastructure project, an Optioneer-generated flyover served as the primary public-facing visualisation on their project website for over 18 months, providing a consistent and clear reference point for the community.

Related use cases:
Project delivery

One platform for the whole programme — from initiation to consent.

Delivery teams are coordinators as much as technical leads. The job is keeping multidisciplinary workstreams aligned, evidence trails intact, and external parties productive — without building those things from scratch on every project.

Project managers
Programme directors
Design managers
Consultants & contractors
PMO

The single project environment

No more version-controlled shapefiles in separate inboxes. All data, route options, metrics, maps and team comments live in one auditable environment.

Automated reporting

RAG status summaries, option comparison tables, constraint breakdowns, and metric dashboards generated directly from the platform. Outputs are 80% aligned with utility reporting formats.

Rapid consultant onboarding

Invite external teams by email and share data access and pre-saved snapshots. 30% of our users are consultants, often with multiple firms collaborating in one space.

Portfolio-level oversight

Inconsistencies across documents are a common source of challenge. By using Optioneer as a single source of truth, you align the story told in public consultations with that told to regulators and technical reviewers.

Replicable project templates

Compound institutional knowledge — Copy constraint frameworks, data configurations, and best practices from completed projects to new ones.

Design to constructor handoff

Use pre-saved snapshots at key stage gates to get incoming contractors or design teams up to speed instantly, with the full decision trail perfectly preserved.

Proof of Performance

200+ experts (internal and external) collaborating across three interfacing projects

Projects develop over years using Optioneer, with role-based access granted to internal and external SMEs. This level of collaboration helps with interface management, retention of project knowledge and onboarding of 3rd parties, e.g. consultants.

Related use cases:

Empower your team today.

Reach out today and see how Optioneer can help streamline your project planning and development.

Client success stories

We’ve had the pleasure of working with global leaders in the utilities industry, find out how they achieved results with Optioneer.

Discuss your project
Learn how Optioneer can accelerate your project development programmes
Ready to revolutionize your project development process? Schedule a no-obligation discussion with our team.
OPTIONEER CAN HELP YOU TO
Cut programme length
Demonstrate a robust selection process
Build consensus with key stakeholders
We’ll help you succeed
Our team of product experts will help set up your project in Optioneer and ensure you and your team achieve your goals.
 *
Please fill in the first name
 *
Please fill in the last name
 *
Please fill in a valid email
Please fill in the company name

By clicking the Get in touch button you accept Continuum Industries’ Privacy Policy and agree to receive promotional messages from Continuum Industries about its products and services. You can unsubscribe at any time by clicking on the link at the bottom of our emails.

Clock
Thank you for contacting us!

We will be in touch with you shortly.

Oops! Something went wrong while submitting the form.