Client success story

National Gas Transmission deploy Optioneer for strategic asset planning

National Gas Transmission (NGT) needed a faster, more consistent way to evaluate pipeline routing options as part of its asset management decision-making — delivering rigorous early-stage analysis at the pace the regulatory environment demands.

The challenge

Asset management decisions move on tight timescales, and traditional early-stage routing studies can’t keep pace. Without rapid, structured option analysis, NGT risks slower answers and less confidence in the trade-offs presented to stakeholders.

As part of its role in managing the gas transmission network in the interest of consumers, NGT frequently needs to compare pipeline routing options at an early feasibility stage. Traditional methods are labour-intensive and can take weeks per option — absorbing time and specialist focus that is needed across the wider priorities of operating a national transmission system.

Conventional approaches also lack the granularity needed to evaluate technical, environmental, and social factors consistently from the outset, and inconsistent GIS datasets across England, Wales, and Scotland add further complexity to the planning process.

The process

Optioneer was configured with NGT’s internal routing guidelines so that pipeline routing options could be generated and compared on a consistent basis, taking technical feasibility, environmental constraints, and social impact into account from the outset.

By standardising the approach, NGT’s asset management team was able to conduct early-stage option analysis in a fraction of the time a manual study would take, with outputs structured to feed directly into internal decision-making and external submissions.

Optioneer was configured with NGT’s internal routing guidelines so that pipeline routing options could be generated and compared on a consistent basis, taking technical feasibility, environmental constraints, and social impact into account from the outset.

By standardising the approach, NGT’s asset management team was able to conduct early-stage option analysis in a fraction of the time a manual study would take, with outputs structured to feed directly into internal decision-making and external submissions.

National Gas

The results

Cost-efficient route options identified: Optioneer generated and compared pipeline routing options consistently, giving NGT defensible early-stage answers without committing full feasibility-study effort.

Reduced assessment timelines: Rather than weeks of manual work per option, Optioneer allowed NGT’s team to share early-stage data across the business and produce structured assessments in a fraction of the time — ultimately keeping costs down for the consumer.

Increased feasibility analysis scope: Standardised metrics let NGT evaluate routes holistically and support informed trade-offs, improving the quality of information available for asset management decisions.

Cost-efficient route options identified: Optioneer generated and compared pipeline routing options consistently, giving NGT defensible early-stage answers without committing full feasibility-study effort.

Reduced assessment timelines: Rather than weeks of manual work per option, Optioneer allowed NGT’s team to share early-stage data across the business and produce structured assessments in a fraction of the time — ultimately keeping costs down for the consumer.

Increased feasibility analysis scope: Standardised metrics let NGT evaluate routes holistically and support informed trade-offs, improving the quality of information available for asset management decisions.

Cost efficient route options identified.

Rapid assessment of options.

Broad range of feasibility criteria configured.

The impact
Traditional method With Optioneer
Route design 9 months 3 months
Resource time 216 days FTE time 72 days FTE time
Route iterations 1–7 days per change 10 mins–2 hrs per change
Major reroute 32 days 10 mins–2 hrs
Bottlenecks High time cost per task Higher output per team member
Communication Email chains, regular meetings, iterations In-platform comments, interactive visuals, real-time adjustments
Use of the Optioneer Continuum tool was highly successful. The team were very efficient, and the rapid turnaround resulted in clear, well-defined pipeline routing options that supported timely decision-making.
Evan Hanson
Asset Planning Manager
National Gas

Have you got a similar project to deliver?

Reach out today and see how Optioneer can help streamline your project planning and development.

Related success stories

We’ve had the pleasure of working with global leaders in the utilities industry, find out how they achieved results with Optioneer.

Discuss your project
Learn how Optioneer can accelerate your project development programmes
Ready to revolutionize your project development process? Schedule a no-obligation discussion with our team.
OPTIONEER CAN HELP YOU TO
Cut programme length
Demonstrate a robust selection process
Build consensus with key stakeholders
We’ll help you succeed
Our team of product experts will help set up your project in Optioneer and ensure you and your team achieve your goals.
 *
Please fill in the first name
 *
Please fill in the last name
 *
Please fill in a valid email
Please fill in the company name

By clicking the Get in touch button you accept Continuum Industries’ Privacy Policy and agree to receive promotional messages from Continuum Industries about its products and services. You can unsubscribe at any time by clicking on the link at the bottom of our emails.

Clock
Thank you for contacting us!

We will be in touch with you shortly.

Oops! Something went wrong while submitting the form.